Justia Civil Procedure Opinion Summaries

Articles Posted in Zoning, Planning & Land Use
by
Montana-Dakota Utilities Co. (“MDU”) appealed, and Lavern Behm cross-appealed a judgment dismissing MDU’s eminent domain action. Because the North Dakota Supreme Court determined the district court misapplied North Dakota law in concluding a taking was not necessary for a public use, the Supreme Court reversed and remanded for trial on eminent domain damages to be awarded to Behm. View "Montana-Dakota Utilities Co. v. Behm" on Justia Law

by
Williams County appealed a the district court’s determination that its oil and gas leases with Twin City Technical LLC, Three Horns Energy, LLC, Prairie of the South LLC, and Irish Oil & Gas Inc. (“Lessees”), were void because the County failed to comply with the public advertising requirements for the lease of public land as provided in N.D.C.C. ch. 38-09. The Lessees sued the County in September 2015, about three and a half years after executing the leases. The North Dakota Supreme Court found record showed the Lessees received a June 2013 letter informing them of potential issues with the County’s mineral ownership. The Lessees contacted the County about the ownership issues by letter in April 2015. The County submitted an affidavit from its auditor stating bonus payments had already been spent and repayment would cause great hardship. Viewing the evidence and reasonable inferences drawn from the evidence in a light favorable to the County, the Supreme Court concluded there were genuine issues of material fact as to whether laches applied to bar the Lessees’ claim for repayment of the bonuses. The Supreme Court reversed that part of the judgment and remand for proceedings related to whether the Lessees’ delay in bringing their lawsuit was unreasonable, and whether the County was prejudiced by the delay. The Court affirmed as to all other issues. View "Twin City Technical LLC, et al. v. Williams County, et al." on Justia Law

by
Robert and Laurie Banderet and other plaintiffs (“Landowners”) appealed a judgment dismissing their complaint seeking declaratory and injunctive relief against the Sargent County Water Resource District and Ransom County Water Resource District relating to a drainage project. The Landowners had sought a judgment declaring: (1) the Drain 11 project could not be funded as maintenance within six years at $4 per acre being assessed to the Landowners; (2) the Landowners were entitled to a hearing and vote on the project; and (3) benefited properties in Ransom County had to be included in the Drain 11 assessment district. The Landowners requested a permanent injunction restraining the Sargent County Water Resource District from proceeding with the Drain 11 project. The North Dakota Supreme Court affirmed, concluding the Landowners were not entitled to equitable relief, and the district court properly dismissed the Landowners’ complaint. View "Banderet,et al. vs. Sargent Count Water Resource District, et al." on Justia Law

by
This appeal centered on the distribution of water to water right 95-0734 in the Twin Lakes-Rathdrum Creek Drainage Basin. Sylte Ranch, LLC, was the current claimant on water right 95- 0734, which dated from 1875 and provided natural flow stockwater from Rathdrum Creek. In September 2016, Idaho Department of Water Resources (IDWR) issued a letter of instructions to the local watermaster in response to a complaint that he was releasing storage water from Twin Lakes contrary to a 1989 Final Decree that established all existing rights to Twin Lakes’ surface waters, tributaries, and outlets. These instructions led Sylte to file a Petition for Declaratory Ruling, arguing that IDWR should set aside and reverse the instructions because they improperly limited water right 95-0734 to Twin Lakes’ natural tributary inflow. Twin Lakes Improvement Association, et al., and Twin Lakes Flood Control District intervened in the case. Following cross motions for summary judgment, IDWR issued a Final Order, in which it upheld the instructions and granted intervenors’ motion for summary judgment. Sylte then sought judicial review and the district court affirmed IDWR’s Final Order. Sylte timely appealed to the Idaho Supreme Court. The Supreme Court affirmed the district court’s determination to uphold IDWR’s Final Order because the instructions complied with the plain language of the 1989 Final Decree. View "Sylte v. IDWR" on Justia Law

by
This case involved a dispute over the planned construction of a high-rise condominium along the Gulf of Mexico in Orange Beach, Alabama. The Perdido Dunes property shared common boundaries with property containing other beachfront condominium buildings. Phoenix East, a Condominium, was a 14-story condominium with 158 residential units located adjacent to and directly east of the Perdido Dunes property. In 2004, Hurricane Ivan effectively destroyed an 8-unit portion of Perdido Dunes. The City's zoning regulations prohibited Perdido Dunes from separating into two parcels, but the City would allow Perdido Dunes to split the PDAI (the condominium association) into two neighborhood associations governed by a master association. The ownership interest in the Master Association would comprise the unit owners of two newly created neighborhood associations, namely the Perdido Dunes Tower Condominium Owners Association, Inc. and the Perdido Dunes 2006 Condominium Owners Association, Inc. The PD Tower Association would serve as the association for Perdido Dunes Tower, a prospective 10-story, 20-unit condominium building measuring 56 feet in length that was to be developed by Perdido Dunes Tower, LLC ("Tower LLC"), on the land where the 8-unit building had been located. The City issued a building permit to Tower LLC in 2008, authorizing it to begin construction of Perdido Dunes Tower. The planned construction was interrupted in 2015, when the City notified Tower LLC of concerns relating to the width of the proposed Perdido Dunes Tower in relation to the neighboring properties, namely Phoenix East and Phoenix VIII. The City directed that Tower LLC could not begin substantial construction on the building, and the City informed Tower LLC that its building permit would be revoked. If the building permit were revoked, Tower LLC would be required to apply for a new permit under updated City building standards, which, according to the trial court's judgment being challenged on appeal, "would have required significant additional undertakings by the Tower LLC to attempt to complete the building of a compliant tower structure." To challenge the proposed Perdido Tower project, the Phoenix entities sued, arguing the consent decree that resulted between the City and the Master Association was void. The Alabama Supreme Court determined the Phoenix VIII Association lacked standing to challenge the consent decree; the Court ruled Phoenix East Association had standing, but "its challenge to the consent decree is unavailing, and the consent decree is affirmed." View "Phoenix East Association, Inc. v. Perdido Dunes Tower, LLC, et al." on Justia Law

by
The City of Lewes and its Historic Preservation Commission approved Ernest and Deborah Nepa’s plans to renovate a house in the historic district. The Nepas violated the conditions of the approvals by building a two story addition on the back of the house and increasing its already nonconforming setbacks from neighboring properties. After the City discovered the violations and issued a stop work order, the Nepas applied to the City’s board of adjustment for three area variances to complete the unauthorized addition; the board turned them down. The Nepas appealed the variance denials to the Superior Court, arguing that the City Code provision used by the board to evaluate their variance applications conflicted with a more lenient state law addressing municipal variances. The Superior Court agreed and reversed the board’s decision. On appeal, the City argued the Superior Court erred because the state statute relied on, 22 Del. C. 327(a)(3), only prohibited the City from loosening the state law requirements for granting a variance. The City was thus free to require stricter standards. The Delaware Supreme Court agreed with the City and reversed the Superior Court’s decision. “As long as the variance standards applied by the City of Lewes’ board of adjustment meet the minimum state statutory standards, nothing in the state statute prohibits the City, through its board of adjustment, from applying variance standards stricter than those set by the State.” View "City of Lewes & The Board of Adjustment v. Nepa" on Justia Law

by
Appellant Jeffrey Severson appealed the trial court’s decision to grant appellees’ the City of Burlington (the City) and the Burlington Conservation Board (the Board) motion to dismiss pursuant to Vermont Rule of Civil Procedure 12(b)(1) and (6). The Burlington Town Center Project (the Project) was a large real estate project that proposed to redevelop the downtown district of the City. The Board met several times to review various aspects of the Project’s permit application. In early October 2017, nearly ten months after the meeting, Severson emailed the Board’s chair and raised concerns over a January 9 meeting. He asserted that the meeting had violated the Open Meeting Law because it had occurred behind locked doors. Severson requested that the Board cure the violation by holding a meeting in compliance with the Open Meeting Law to conduct a review of the most current version of the Project’s plan and to ratify the other, non-Project related Board actions taken at the January 9 meeting. The Board met on November 13, during which it reviewed a memorandum prepared by the City’s legal counsel and the relevant facts of Severson’s allegations, including information on the staffing procedure of the library on nights when public meetings were scheduled there. The Board determined that no Open Meeting Law violation had occurred. Severson filed suit, and when his case was dismissed, he appealed, arguing the trial court erred when it determined he, as a member of the Board, did not have standing because he did not allege an injury that was actionable under Vermont’s Open Meeting Law. The Vermont Supreme Court found that dismissal of Severson’s claim was proper, and thus affirmed. View "Severson v. City of Burlington & Burlington Conservation Board" on Justia Law

by
In 2013, a small business jet crashed into a Georgia Power Company transmission pole on Milliken & Company’s property near the Thomson-McDuffie Regional Airport in Thomson, Georgia. The two pilots were injured and the five passengers died. In the wake of the crash, the pilots and the families of the deceased passengers filed a total of seven lawsuits against multiple defendants, including Georgia Power and Milliken. The complaints in those seven suits alleged that a transmission pole located on Milliken’s property was negligently erected and maintained within the airport’s protected airspace. The record evidence showed Georgia Power constructed the transmission pole on Milliken’s property for the purpose of providing electricity to Milliken’s manufacturing-plant expansion, and that the pole was constructed pursuant to a 1989 Easement between Georgia Power and Milliken. In each of the seven suits, Milliken filed identical cross-claims against Georgia Power, alleging that Georgia Power was contractually obligated to indemnify Milliken “for all sums that Plaintiffs may recover from Milliken” under Paragraph 12 of the Easement. Georgia Power moved for summary judgment on the crossclaims, which were granted. The trial court reasoned Paragraph 12 of the Easement operated as a covenant not to sue, rather than as an indemnity agreement, because it “nowhere contains the word ‘indemnity’” and “it is not so comprehensive regarding protection from liability.” The Court of Appeals affirmed summary judgment to six cases. Rather than adopt the trial court’s reasoning, the appellate court held that the provision was an indemnity agreement and affirmed the trial court by applying Georgia’s anti-indemnity statute, OCGA 13-8-2 (b), to determine that Paragraph 12 of the Easement was “void as against public policy,” a theory argued before the trial court but argued or briefed before the Court of Appeals. The Georgia Supreme Court determined the Court of Appeals erred in its construction and application of OCGA 13-8-2(b), vacated the judgment and remanded for the lower court to consider whether, in the first instance, the trial court’s rationale for granting Georgia Power’s motions for summary judgment and any other arguments properly before the Court of Appeals. View "Milliken & Co. v. Georgia Power Co." on Justia Law

by
In 2010, Appellee City of Lebanon (the “City”) was considering creation of a business improvement district (a “BID”), a type of Neighborhood Improvement District (“NID”) to revitalize its downtown area. After a hearing, at which citizens voiced their comments, the City accepted a plan devised by City officials and hired consultants as final and sent another letter to property owners and lessees within the proposed BID, advising how to file an objection, or to vote against the establishment of the Lebanon BID. Appellant Edward Schock, the owner of a non-exempt property in the Lebanon BID, filed suit at the county court under the caption: “Complaint for Declaratory Judgment to Declare Bid Dead.” In the complaint, Appellant advanced the position that, under NIDA, “the objection threshold is 40% of the assessed parcels,” as opposed to forty percent of all parcels within the geographic boundaries of a BID. Given that, by his calculus, only the owners of 280 properties within the geographic boundaries of the BID were eligible to vote, Appellant concluded that the final plan had been vetoed by the 132 negative votes. The City filed preliminary objections in the nature of a demurrer, contending that the term “affected property owners,” in Section 5(f)(2), unambiguously encompasses all of the owners of properties within the geographic boundaries of a BID, regardless of whether they will be subject to or exempt from monetary assessments. The Pennsylvania Supreme Court found, as did the court of common pleas, there were substantial, competing policy considerations in the design of the voting scheme pertaining to the establishment of NIDs. “Ultimately, although we find the shifting terminology within the Act to be awkward and ambiguous, we conclude that the statute’s veto provisions pertaining to final NID plans concern only assessed property owners.” The order of the Commonwealth Court was reversed and the matter remanded for entry of declaratory judgment reflecting the Supreme Court’s opinion. View "Schock. v. City of Lebanon" on Justia Law

by
The issue presented for the Pennsylvania Supreme Court’s review in this case centered on the question of whether a municipality, in addressing a natural gas extraction company’s conditional use application for the construction and operation of a well site, could consider as evidence the testimony of residents of another municipality regarding the impacts to their health, quality of life, and property which they attribute to a similar facility constructed and operated by the same company in their municipality. After careful review, the Supreme Court held such evidence could be received and considered by a municipality in deciding whether to approve a conditional use application, and, thus, vacated the Commonwealth Court’s order, and remanded this matter to that court, with instructions to remand this matter to the trial court for further consideration. View "EQT Production v. Boro of Jefferson Hills" on Justia Law