Justia Civil Procedure Opinion Summaries

Articles Posted in Construction Law
by
Waypoint, the project owner, entered into a construction contract with Team Contractors, the general contractor, and entered into an architectural contract with HCA. HCA then retained KLG as the project's engineer. Team filed suit and subsequently prevailed against the engineers and architects for negligence, but not against the owner for breach of contract. After a finding that the initial verdict had an irreconcilable conflict, a second trial was held just on the breach of contract claim. The jury then reached a verdict for the general contractor, and the owner appealed.The Fifth Circuit vacated the district court's judgment and remanded for the district court to reinstate the original verdict. The court held that if the answers to written questions require jurors to apply the instructed law to their fact-findings, thereby fully explaining who prevails on all claims against a single defendant, and if relevant, the amount of any monetary award, that is sufficient for a Federal Rule of Civil Procedure 49(b) verdict. Though in this case the jurors were not given, as Rule 49(b) states, "forms for a general verdict" and also for answers to written questions, jurors applied their instructions on the law to their fact finding and found there had been no breach of contract. The court held that the result fully resolved the claim against Waypoint. The court stated that the general verdict is incomplete in Rule 49(b) terms, but it is sufficient. The court also held that Team waived any argument to have the verdict set aside. Finally, the court remanded for the district court to consider attorneys' fees. View "Team Contractors, LLC v. Waypoint NOLA, LLC" on Justia Law

by
Caliber Paving Company, Inc. (Caliber) sued Rexford Industrial Realty and Management, Inc. (Rexford) for intentional interference with a contract between Caliber and Steve Fodor Construction (SFC). The trial court granted Rexford’s motion for summary judgment on the ground that Rexford, although not a party to the contract, had an economic interest in it and therefore could not be liable in tort for intentional interference with contract. Caliber appealed. In a case of first impression, the Court of Appeal held that under Applied Equipment Corp. v. Litton Saudi Arabia Ltd., 7 Cal.4th 503 (1994), a defendant who is not a party to the contract or an agent of a party to the contract is a noncontracting party or stranger to the contract and, regardless whether the defendant claims a social or economic interest in the contractual relationship, may be liable in tort for intentional interference with contract. Applied Equipment did not confer immunity for intentional interference with contract on noncontracting parties having a social or economic interest in the contractual relationship from liability. The Court also concluded Caliber submitted admissible evidence sufficient to meet its burden of raising a triable issue of fact as to whether Rexford interfered with the contract between SFC and Caliber. Judgment was reversed and the matter remanded for further proceedings. View "Caliber Paving Co. v. Rexford Industrial Realty and Management" on Justia Law

by
In 2014, plaintiffs filed suit against defendants Shappell Industries and Toll Brothers, Inc. (the Developer) for construction defects arising out of the construction of two residences in a community called San Joaquin Hills. The complaint also named Doe defendants, including two causes of action against unnamed engineers, Does 101-125. Plaintiffs claimed that in 2017, some two years and nine months after the suit was filed, the Developer produced discovery that identified Petra Geosciences, Inc. On August 2, 2017, while the matter was still stayed pending the judicial reference proceeding, plaintiffs filed an amendment to the complaint naming Petra as Doe 101. At the same time, it filed a certificate of merit as required by section 411.35 (certificate of merit required before serving the complaint in a malpractice action against an engineer). Plaintiffs personally served Petra with the summons and complaint on August 9, 2017, three years and 38 days after the complaint was filed. The trial court dismissed plaintiffs’ complaint against defendant Petra because plaintiffs had not served Petra with a summons and complaint within three years, as required by Code of Civil Procedure section 583.210. Plaintiffs appealed the subsequent dismissal, contending the court erred in computing the three-year period. The Court of Appeal found the trial court had stayed the matter for nine months while the parties engaged in a prelitigation alternative dispute resolution procedure mandated by a contract. The court did not exclude that period from the three-year calculation. The question was, did that stay affect service, thereby extending the time to serve Petra? The Court concluded it likely did, but that remand was necessary for further findings. View "Steciw v. Petra Geosciences, Inc." on Justia Law

by
After defending the general contractor in two construction defect actions, general liability insurer St. Paul Mercury Insurance Company (St. Paul) sought reimbursement of defense costs under an equitable subrogation theory against six subcontractors (defendants) that had worked on the underlying construction projects and whose contracts required them to defend the general contractor in suits involving allegations related to their work. After a bench trial, the court denied St. Paul’s claim. Relying on Patent Scaffolding Co. v. William Simpson Constr. Co., 256 Cal.App.2d 506, 514 (1967), the trial court concluded St. Paul had not demonstrated it was fair to shift all of the defense costs to defendants because their failure to defend the general contractor had not caused the homeowners to bring the construction defect actions. St. Paul argued this conclusion misconstrued the law governing equitable subrogation and therefore constitutes an abuse of discretion. To this, the Court of Appeal agreed: (1) a cause of action based on equitable subrogation allowed an insurer to step into the shoes of its insured and recover only what the insured would be entitled to recover from the defendants; and (2) the appropriate inquiry should have been whether defendants’ failure to defend the general contractor caused St. Paul to incur the defense costs, not whether that failure caused the underlying lawsuits. Judgment was reversed and the matter remanded to the trial court to grant judgment in St. Paul's favor and for a determination of defense costs each defendant owed. View "Pulte Home Corp. v. CBR Electric, Inc." on Justia Law

by
Plaintiff Riverbend Condo Association appealed a superior court order dismissing its complaint against defendant Groundhog Landscaping and Property Maintenance, Inc., on res judicata grounds. In 2017, plaintiff brought a breach of contract action against defendant. Neither party appeared at the scheduled trial management conference set by the superior court. The superior court thus canceled trial and dismissed the case. Plaintiff filed a "motion to reopen," asking the court to reopen the matter and reschedule the trial management conference. The superior court denied the motion, stating that plaintiff's pleading constituted an untimely motion to reconsider. Plaintiff thereafter brought a second action, alleging among other things, breach of contact. Defendant moved to dismiss, arguing that the action was barred by res judicata. The trial court ultimately granted defendant's motion. On appeal, plaintiff contended its complaint was not barred by the trial court’s dismissal of its first action against defendant, as that dismissal was not a final judgment on the merits. Finding no reversible error, the New Hampshire Supreme Court affirmed. View "Riverbend Condo Association v. Groundhog Landscaping & Property Maintenance, Inc." on Justia Law

by
Subcontractor Construction Drilling, Inc. (CDI) appealed a trial court’s judgment on the merits in its breach-of-contract claim against Engineers Construction, Inc. (ECI). CDI contended the trial court erred in: (1) holding that the terms of the parties’ subcontract required CDI to request a change order before it billed ECI for “drilling in obstructions” in excess of CDI’s bid price; (2) denying CDI’s motions to reopen the evidence and for a new trial; and (3) awarding ECI $234,320 in attorneys’ fees under the Prompt Payment Act. ECI cross-appealed, arguing the trial court improperly allowed CDI’s owner to offer opinion testimony absent a finding of reliability under Vermont Rule of Evidence 702 and maintaining that his testimony could not have met this standard in any event. Therefore, should the Vermont Supreme Court reverse the trial court’s denial of CDI’s breach-of-contract claim, ECI asserted the matter had to be remanded for a new trial without such testimony. The Court affirmed the trial court, and therefore did not reach the issue raised in ECI’s cross-appeal. View "Construction Drilling, Inc. v. Engineers Construction, Inc." on Justia Law

by
Russell Construction of Alabama, Inc. ("Russell"), appealed a circuit court order that vacated an arbitration award in favor of Russell and against Christopher Peat. In 2015, Russell and Peat entered into a contract pursuant to which Russell agreed to construct a residence for Peat on "a cost plus a fee basis." The documents executed in connection with the contract provided, in the event of a controversy or dispute, first for mediation and then for arbitration in accordance with the rules of the American Arbitration Association. Upon completion of the residence, a dispute arose between Russell and Peat regarding Russell's performance and the balance due Russell under the contract. In January 2018, Russell filed a formal demand for arbitration, seeking $295,408 allegedly due from Peat for the construction of the residence. Peat counterclaimed, alleging breach of fiduciary duty and breach of contract and disputing his consent to costs incurred by Russell; Peat sought specific performance and an award of $255,000 on his counterclaims. Thereafter, in May 2018, the parties reached, as a result of mediation, a settlement agreement. In essence, the settlement agreement required Russell to make certain repairs to the residence; required Peat to pay Russell $245,408 on or before June 15, 2018, at which time Russell agreed to release its recorded lien; and required Peat to deposit into escrow an additional $50,000 to ensure completion, by the end of August 2018, of a "punch-list" to the satisfaction of a third-party "Construction Consultant." The Alabama Supreme Court determined the circuit court did not err to the extent that it set aside the judgment entered pursuant to the arbitrator's Final Award. The Court affirmed the trial court's July 25, 2019 order to the extent that it vacated any judgment on the arbitrator's Final Award related to Russell's and Peat's breach of the provisions of the settlement agreement that remained in effect after the Modified Partial Final Award and the distribution of the outstanding $50,000 at issue. The Court reversed that same order to the extent it purported to vacate any judgment on the Modified Partial Final Award of $258,959.89 and remanded this case for further proceedings. View "Russell Construction of Alabama, Inc. v. Peat" on Justia Law

by
Several insurance companies (the Insurers) appealed the denial of their motions to intervene in a construction defect action between a property owners' association (the Association) and a number of construction contractors and subcontractors (the Insureds). The underlying construction defect action proceeded to trial, resulting in a verdict for the Association. After review, the South Carolina Supreme Court determined the Insurers were not entitled to intervene as a matter of right, and the trial court did not abuse its discretion in denying them permissive intervention. However, the Court held the Insurers had a right to a determination of which portions of the Association's damages are covered under the commercial general liability (CGL) policies between the Insurers and the Insureds. The Court also recognized that the Insurers had the right and ability to contest coverage of the jury verdict in a subsequent declaratory judgment action. "In that action, the Insurers and the Insureds will be bound by the existence and extent of any jury verdict in favor of the Association in the construction defect action. However, they will not be bound as to any factual matters for which a conflict of interest existed, such as determining what portion of the total damages are covered by any applicable CGL policies." View "Builders Mutual Insurance Company" on Justia Law

by
The Supreme Court reversed the judgment of the court of appeals dismissing Appellant's appeal of the trial court's grant of summary judgment for Plaintiff and against Defendants for want of jurisdiction, holding that, contrary to the decision of the court of appeals, the trial court's judgment was final and appealable.Plaintiff sued Defendants for declaratory judgment and monetary damages arising from a commercial construction project. The trial court awarded summary judgment in favor of Plaintiff. Despite the trial court's confirmation of its intent to render a final judgment, the court of appeals concluded that no final judgment had been rendered. The Supreme Court reversed, holding that the court of appeals erred by analyzing the record for evidence of finality after the trial court provided a clear and unequivocal statement that it had intended the appealed-from order to be a final judgment. View "Bella Palma, LLC v. Young" on Justia Law

by
A construction contractor’s employees were injured on the job and received workers’ compensation benefits from their employer. The workers later brought a negligence suit against three other corporations: the one that had entered into the construction contract with their employer, that corporation’s parent corporation, and an affiliated corporation that operated the facility under construction. The three corporations moved for summary judgment, arguing that all three were “project owners” potentially liable for the payment of workers’ compensation benefits and therefore were protected from liability under the exclusive liability provision of the Alaska Workers’ Compensation Act. The superior court granted the motion, rejecting the workers’ argument that status as a “project owner” was limited to a corporation that had a contractual relationship with their employer. After review, the Alaska Supreme Court concluded a project owner, for purposes of the Act, "must be someone who actually contracts with a person to perform specific work and enjoys the beneficial use of that work." Furthermore, the Court found the workers raised issues of material fact about which of the three corporate defendants satisfied this definition. Judgment was therefore reversed and the matter remanded for further proceedings. View "Lovely, et al. v Baker Hughes, Inc., et al." on Justia Law