In re Petition of Stowe Cady Hill Solar, LLC

by
Stowe Cady Hill Solar (Cady Hill) applied to the Vermont Public Utility Commission for a certificate of public good to construct a group net-metered solar array in the Town of Stowe. The Commission dismissed Cady Hill’s application after finding that the application was incomplete because two adjoining landowners were not given notice that the application had been filed contemporaneous with that filing. After review, the Vermont Supreme Court held that Cady Hill’s application met the completeness requirement as that requirement has been applied in the Commission’s prior decisions and, therefore, the application should not have been dismissed. View "In re Petition of Stowe Cady Hill Solar, LLC" on Justia Law